Work Update

Work is going well. We are about 95% done with our self perform structural concrete, i.e. the fun work. We are pouring one big slab every week in what is the lower level of the parking garage. There are drains to slope to and a lot of fine grading and semi-challenging work. The most challenging part is keeping everyone busy and on task. Unfortunately and Fortunately we have the first layoffs of the job tomorrow. Most of the guys know already if it involves them, they also know it is inevitable. It's life in the union.